Eight components are now in production, including the most complex ones: the end cover with fuel nozzles, the transition piece and the combustion liner. Vacuum brazing and electron beam welding were developed for the nozzles, and the nozzle swirlers are made by selective laser melting (3D printing). More than 50 tooling items were designed and built for the transition piece, which carries a Russian thermal barrier coating on its inner surface.
A trial assembly of the combustion chamber in June 2026 passed without remarks. The components have been shipped to an operating Gazprom compressor station, where they will be installed on a T32 unit for endurance testing of 5,000 equivalent operating hours.
The T32 turbine powers GPA-32 Ladoga gas compressor units and was built under licence from GE's MS5002E design. The localisation programme covers 78 items, and the turbine hot gas path was fully localised by 2024.
SeverEnergoProject performs borescope inspection of combustion chambers and hot gas paths, as well as overhaul of gas turbine units.
Source: Gas Turbine Technologies (gtt.ru)