According to GasTurbineHub and Bloomberg (April 2026), gas turbine prices have risen by about 195% against 2019 levels. Several structural factors are driving the gap between supply and demand: large-scale construction of data centres for artificial intelligence, electrification of transport infrastructure, and tighter grid reliability requirements in the face of intermittent renewable generation.
The largest manufacturers — GE Vernova, Siemens Energy and Mitsubishi Power — have announced capacity expansion programmes. Siemens Energy intends to invest several billion dollars in new production sites in the United States. Even so, closing the gap in the short term looks difficult: commissioning new production lines takes years.
In response to the capacity shortage, OEMs are tightening contract terms: fixing advance payments, introducing price escalation clauses and reducing the number of slots available to new customers. Lead times for gas turbines above 100 MW already exceed the norms of previous years, forcing project developers and EPC contractors to revise their schedules.
For end users — power plant operators, oil and gas companies and industrial enterprises — this means booking equipment well in advance and planning procurement far more carefully. Analysts do not rule out sustained price pressure at least until 2028, when new capacity at the leading OEMs may partially come on stream.
With new turbines in short supply, repair is becoming more attractive than replacement: SeverEnergoProject performs overhaul and maintenance of Solar Turbines gas turbine units and supplies spare parts from stock.